|
Milestone Schedule
The project must be completed
before the scheduled hunter orientation days and the current
ranger imposed deadline is November 7, 2010. To support that
deadline the following milestone schedule is planned;
Initial meeting with Ranger
McClevey to discuss potential projects - August 7
COMPLETED
Project approval – September
14, 2010 COMPLETED
Recruit team leaders NLT –
September 16, 2010 COMPLETED
Final coordination meeting
with Ranger McClevey to confirm schedule dates -September 17,
2010 COMPLETED
Leader training with the
ranger – October 2, 2010 COMPLETED
Leader walk through of the
terrain – October 16, 2010 NOT REQUIRED BECAUSE OF THE
THOROUGHNESS OF THE WORK PERFORMED ON OCTOBER 2ND.
Primary work date – October
23, 2010 COMPLETED
Alternate work date – October
30, 2010 NOT REQUIRED (Flagging of the Great Marsh Trail
(temporarily halted by lack of staples was completed late
October 23rd)
Scout assistance at Hunter
Scouting day (as required) – November 7, 2010
|